FYI’s high purity alumina pilot plant commences trial production

1431
FYI Resources CEO, Roland Hill
Media Release

FYI Resources Ltd (ASX: FYI) is pleased to inform the market that the Company has today commenced the trial production of high purity alumina (HPA) at its recently constructed and commissioned pilot plant.

FYI’s dedicated pilot plant, located in Welshpool, Western Australia, is the result of 12 months of research and development and refining of an innovative process flowsheet which is designed to efficiently and cost effectively process aluminous clay (kaolin) and refine it into the high value product, HPA.

The pilot plant is scheduled to run continuously for 7 days on a 24 hours a day basis to demonstrate “end to end” processing of FYI’s HPA process flowsheet. The key parameters for the plant are:

Item Detail
Plant details Dedicated, purpose built, 3 stage hydrochloric acid leach and precipitation circuit
Pilot Plant trials commence 2 October 2019
Operating time Continuous (24/7) / 2 shifts per day
Operating period 1 week
Plant design Innovative modular “end to end”
Output 1.0 Kg per hour
Target grade >99.99% Al2O3

The pilot plant has been collaboratively designed and engineered by FYI’s joint HPA Study Managers – GR Engineering Services and Independent Metallurgical Operations.

Adertisement

Commenting on the commencement of trial production, FYI Managing Director, Roland Hill, said “We are absolutely delighted to be starting trial production of HPA from our purpose designed and built pilot plant. This occasion represents a major technical and corporate milestone in the commercialisation of the Company’s HPA strategy and is the culmination of a serious amount of dedicated and innovative thinking and effort to bring the plant to production. We have great confidence that the trial outcomes will validate our prefeasibility study results and provide excellent data for inputs into our definitive feasibility study that is currently being compiled”.

The resulting HPA end product will be checked for quality control and assurance before being forwarded to end-user and customer groups that FYI has been in advanced discussions with regarding HPA marketing and off-take arrangements.

FYI was recently awarded Lead Agency support from the WA Department of Jobs, Tourism, Science and Innovation by the Western Australian Premier, Mr Mark McGowan, for FYI’s role in contributing to the delivery of the WA government’s Future Battery Industry Strategy. The pilot plant is a critical phase in the project development of the Cadoux Kaolin HPA project.